Cement plant 500 tons per day:

  1. Raw material preparation section - crushing, drying and storage;
  2. Section for preparing the raw material mixture (charge) - based on a ball mill Ф2.6×10m;
  3. Warehouse for homogenization of raw material mixture (charge);
  4. Furnace feed section and preheating cyclones (5 cyclones);
  5. Clinker firing section - based on a rotating kiln Ф3.5×60m;
  6. Clinker grinding section - based on a ball mill Ф2.4×13m;
  7. Cement storage section;
  8. Cement packaging section;
  9. Automation system;
  10. Laboratory.

Operating principle of a full cycle cement plant:

1. Initial raw materials - limestone, clay, additives - are delivered to the warehouse, where crushing, drying and loading into storage silos is carried out;

2. From the silos, the material is unloaded onto belt dispensers and enters the ball mill;

3. Grinding is carried out in a ball mill to a fraction of 100-200 microns and discharged into a homogenization silo;

4. In the homogenization silo, the composition of the raw materials is equalized to obtain a final product that is stable in composition;

5. From the homogenization silo, the raw material mixture enters the preheating cyclones, and is then fired in a rotary kiln at temperatures up to 1500 degrees and passes through a cooler into an intermediate bunker;

6. From intermediate bunkers, clinker, gypsum and other additives are dosed, which go into a ball mill and are ground to the required fineness (according to GOST - the residue on a sieve of 80 microns is no more than 15%);

7. The finished product (cement) is unloaded into silos for further shipment to cement trucks or sent to the bagging line.